A Bill of Quantities, often called a BOQ or BoQ, is a structured document listing the measured work required for a construction project.

For UK builders and contractors, a clear BOQ can support tender pricing, subcontract enquiries, procurement, valuations and cost control. It provides a consistent basis for pricing the same scope of work.

This guide explains what a BOQ includes, how it is prepared and how a typical document may be structured.

WHAT IS A BILL OF QUANTITIES?

A Bill of Quantities is a measured schedule of construction work. It normally includes:

The document is prepared from the available drawings, specifications, schedules and tender information. Depending on the project, the measurement may follow the principles of the RICS New Rules of Measurement, including NRM2 for building works.

The BOQ gives contractors a common pricing document. Each tenderer can enter rates against the same descriptions and quantities.

This makes tender returns easier to review and compare.

You can read more about our Bills of Quantities service for UK builders and contractors.

WHAT A BOQ IS NOT

Several construction documents are related to a BOQ but serve different purposes.

A BOQ Is Not the Same as a Construction Estimate

A BOQ sets out the measured work. It may be issued without rates so that a contractor can price it.

A construction estimate applies costs to the measured work. It may include:

A BOQ can therefore form part of a wider construction estimate.

A BOQ Is Not the Same as a Quantity Take-Off

A quantity take-off is the measurement process. It identifies quantities from drawings and specifications.

The BOQ is the structured document produced from that measurement. It converts the measured information into clear, priceable work items.

A BOQ Is Not a Specification

A specification explains the required standards, materials, workmanship and performance.

A BOQ describes and measures the work. It should align with the specification but does not replace it.

Where information is incomplete, assumptions and clarifications should be recorded. A BOQ should not present uncertain information as confirmed scope.

WHO USES A BILL OF QUANTITIES?

BOQs are used by several parties during tendering and construction.

Main Contractors

Main contractors use BOQs to:

Subcontractors

Subcontractors may receive relevant BOQ sections for groundworks, roofing, mechanical services, electrical work, drylining or other trade packages.

A defined quantity and description helps the subcontractor price the same work as other tenderers.

Clients and Developers

Clients can use a BOQ to review tender returns and understand how the overall price is distributed across different work sections.

It can also support budget review and cost reporting.

Quantity Surveyors and Commercial Teams

Quantity surveyors use BOQs for tender analysis, valuations, variations and cost control.

The document can remain useful after the tender stage, particularly where the contract or procurement process uses measured quantities.

A BOQ is more likely to be required on larger, formal or traditionally procured projects. It may also be appropriate for smaller projects where the parties need a clear basis for tender comparison.

HOW IS A BOQ BUILT?

A professional BOQ is prepared through a structured measurement process.

Architectural drawings, specifications and measurement tools arranged for a quantity take-off

1. Review the Project Documents

The estimator or quantity surveyor reviews:

The review confirms what information is available and identifies gaps that may affect measurement.

2. Confirm the Scope

The scope should be confirmed before detailed measurement begins.

This may include confirming:

3. Complete the Quantity Take-Off

The drawings are digitally measured to identify lengths, areas, volumes and item counts.

Examples include:

The measurements are then checked and grouped into logical work sections.

4. Compile the BOQ

The measured information is converted into clearly described BOQ items.

Each item should be sufficiently clear for a contractor, supplier or subcontractor to understand what is included.

5. Check and Present the Document

The completed document should be reviewed for:

SAMPLE BOQ STRUCTURE FOR A UK PROJECT

The exact structure depends on the project and measurement requirements. However, a typical residential or small commercial BOQ may include the following sections.

Structured construction tender document with work-section tabs and cost summary

1. Preliminaries

Typical items include:

2. Substructure

This section may include:

3. Superstructure

Typical items include:

4. Internal Finishes and Fittings

This may include:

5. External Works

Common items include:

6. Services

Depending on the project, services may include:

7. Provisional Sums and Allowances

Provisional sums are allowances for work that cannot yet be fully measured or defined.

Examples may include:

Prime cost items may also be included for items such as sanitaryware, kitchen equipment or specialist finishes where the final selection is not confirmed.

The basis of each allowance should be explained.

8. Dayworks

A daywork schedule sets out rates for work instructed on a time and materials basis.

It may include:

9. Overheads and Profit

The BOQ may include separate entries for:

The treatment of overheads and profit depends on the tender instructions and procurement arrangement.

SAMPLE BOQ LINE ITEM FORMAT

A typical BOQ schedule may use the following columns:

Ref Description Unit Quantity Rate (£) Total (£)
A.1.1 Excavate trench foundations in ordinary ground and remove surplus material 45.00
A.1.2 Concrete strip foundations, including placing and compacting 18.00
A.1.3 Engineering brickwork below damp-proof course 38.00
A.1.4 Damp-proof membrane to ground floor areas, including laps and joints 85.00

The description, unit and quantity must relate to one another. A contractor should be able to understand the work without repeatedly interpreting the drawings.

You can also download a sample BOQ workbook to review a practical Excel layout.

WHY MEASUREMENT, DESCRIPTIONS AND UNITS MATTER

Clear measurement supports fair tender comparison.

If one contractor prices 100 square metres and another assumes 100 linear metres, their tender returns cannot be compared meaningfully.

Clear descriptions also reduce the risk of different interpretations. A useful description may identify:

Poor BOQs can create several problems:

A systematic BOQ does not remove every project risk. It does provide a clearer record of what was measured, what was assumed and what remains to be confirmed.

HOW ESTIMATE EXACT PREPARES A BESPOKE BOQ

Estimate Exact prepares BOQs for UK builders, contractors, subcontractors, developers and construction professionals.

Our process is structured around your project requirements.

We Review Your Documents

We review the drawings, specifications, schedules and tender information supplied.

We Confirm the Scope

We clarify the required work sections, format, measurement approach, exclusions and assumptions.

We Complete the Measured Take-Off

Our in-house estimators measure the works from the available information. We do not rely on generic templates or outsource the work to external agencies.

We Prepare the BOQ

The completed document can include structured descriptions, units, quantities, pricing columns, preliminaries, allowances, provisional sums, assumptions and clarifications.

We Add Pricing Where Required

If you need a priced estimate as well as an unpriced BOQ, we can include labour, materials, plant, subcontractor costs and appropriate live supplier pricing.

The final document is professionally presented and suitable for tendering, subcontract enquiries, budgeting or project cost control.

FIXED-FEE PRICING AND AGREED DELIVERY

The fee depends on the project size, complexity, information available and required output.

After reviewing your documents, we confirm:

This gives you a clear position before work begins.

FREQUENTLY ASKED QUESTIONS

Can you prepare an unpriced BOQ?

Yes. We can provide a measured BOQ ready for your own estimator or commercial team to price.

Can you price the BOQ as well?

Yes. We can combine the BOQ with a full construction estimate covering labour, materials, plant and subcontractor costs.

Can you measure one trade package only?

Yes. We can prepare quantity take-offs or BOQs for individual packages, including groundworks, roofing, carpentry, finishes, plumbing and electrical works.

Do you use NRM2?

Yes, where appropriate to the project. The format can also be adapted to suit the tender requirements and your preferred commercial structure.

What information do you need?

Ideally, send architectural and structural drawings, specifications, schedules, tender documents and any existing scope information.

If information is incomplete, we can identify assumptions and clarifications where sufficient information is available.

Do you support contractors throughout the UK?

Yes. Our remote estimating service supports UK builders, contractors and construction professionals.

READY TO REQUEST A BOQ?

Send us your drawings, specifications and tender documents. We will review the requirements and provide a clear fixed quotation with an agreed delivery date.

For a measured BOQ, quantity take-off or outsourced construction estimating service, contact Estimate Exact to discuss your project.

You can also submit your drawings through our Bills of Quantities service.

Leave a Reply

Your email address will not be published. Required fields are marked *